Donate NowH.R.5892 - Hydropower Regulatory Efficiency Act of 2012
To improve hydropower, and for other purposes.
| Version | Word Count | Changes From Previous Version | Percent Change |
|---|---|---|---|
| Introduced in House | 1,861 | n/a | n/a |
| Reported in House | 1,973 | 6 | 4% |
| Engrossed in House | 1,839 | 9 | 6% |
| Referred in Senate | 1,842 | 5 Show Changes Hide Changes | 2% |
Key: changed or removed text inserted or modified text

Loading Bill Text
Rollover any line of text to comment and/or link to it.
HR 5892 EHRFSCommentsClose CommentsPermalink

112th CONGRESSCommentsClose CommentsPermalink

2d SessionCommentsClose CommentsPermalink

H. R. 5892CommentsClose CommentsPermalink

IN THE SENATE OF THE UNITED STATESCommentsClose CommentsPermalink

July 10, 2012CommentsClose CommentsPermalink
July 10, 2012CommentsClose CommentsPermalink

Received; read twice and referred to the Committee on Energy and Natural ResourcesCommentsClose CommentsPermalink

AN ACTCommentsClose CommentsPermalink

To improve hydropower, and for other purposes.CommentsClose CommentsPermalink

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, CommentsClose CommentsPermalink

SECTION 1. SHORT TITLE; TABLE OF CONTENTS.
(a) Short Title- This Act may be cited as the ‘Hydropower Regulatory Efficiency Act of 2012’.CommentsClose CommentsPermalink

(b) Table of Contents- The table of contents of this Act is as follows:CommentsClose CommentsPermalink

Sec. 1. Short title; table of contents.CommentsClose CommentsPermalink

Sec. 2. Findings.CommentsClose CommentsPermalink

Sec. 3. Promoting small hydroelectric power projects.CommentsClose CommentsPermalink

Sec. 4. Promoting conduit hydropower projects.CommentsClose CommentsPermalink

Sec. 5. FERC authority to extend preliminary permit periods.CommentsClose CommentsPermalink

Sec. 6. Promoting hydropower development at nonpowered dams and closed loop pumped storage projects.CommentsClose CommentsPermalink

Sec. 7. DOE study of pumped storage and potential hydropower from conduits.CommentsClose CommentsPermalink

SEC. 2. FINDINGS.
Congress finds that--CommentsClose CommentsPermalink

(1) the hydropower industry currently employs approximately 300,000 workers across the United States;CommentsClose CommentsPermalink

(2) hydropower is the largest source of clean, renewable electricity in the United States;CommentsClose CommentsPermalink

(3) as of the date of enactment of this Act, hydropower resources, including pumped storage facilities, provide--CommentsClose CommentsPermalink

(A) nearly 7 percent of the electricity generated in the United States; andCommentsClose CommentsPermalink

(B) approximately 100,000 megawatts of electric capacity in the United States;CommentsClose CommentsPermalink

(4) only 3 percent of the 80,000 dams in the United States generate electricity, so there is substantial potential for adding hydropower generation to nonpowered dams; andCommentsClose CommentsPermalink

(5) according to one study, by utilizing currently untapped resources, the United States could add approximately 60,000 megawatts of new hydropower capacity by 2025, which could create 700,000 new jobs over the next 13 years.CommentsClose CommentsPermalink

SEC. 3. PROMOTING SMALL HYDROELECTRIC POWER PROJECTS.
Subsection (d) of section 405 of the Public Utility Regulatory Policies Act of 1978 (

SEC. 4. PROMOTING CONDUIT HYDROPOWER PROJECTS.
(a) Applicability of, and Exemption From, Licensing Requirements- Section 30 of the Federal Power Act (

(1) by striking subsections (a) and (b) and inserting the following:CommentsClose CommentsPermalink

‘(a)(1) A qualifying conduit hydropower facility shall not be required to be licensed under this part.CommentsClose CommentsPermalink
‘(2)(A) Any person, State, or municipality proposing to construct a qualifying conduit hydropower facility shall file with the Commission a notice of intent to construct such facility. The notice shall include sufficient information to demonstrate that the facility meets the qualifying criteria.CommentsClose CommentsPermalink
‘(B) Not later than 15 days after receipt of a notice of intent filed under subparagraph (A), the Commission shall--CommentsClose CommentsPermalink
‘(i) make an initial determination as to whether the facility meets the qualifying criteria; andCommentsClose CommentsPermalink
‘(ii) if the Commission makes an initial determination, pursuant to clause (i), that the facility meets the qualifying criteria, publish public notice of the notice of intent filed under subparagraph (A).CommentsClose CommentsPermalink
‘(C) If, not later than 45 days after the date of publication of the public notice described in subparagraph (B)(ii)--CommentsClose CommentsPermalink
‘(i) an entity contests whether the facility meets the qualifying criteria, the Commission shall promptly issue a written determination as to whether the facility meets such criteria; orCommentsClose CommentsPermalink
‘(ii) no entity contests whether the facility meets the qualifying criteria, the facility shall be deemed to meet such criteria.CommentsClose CommentsPermalink
‘(3) For purposes of this section:CommentsClose CommentsPermalink
‘(A) The term ‘conduit’ means any tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.CommentsClose CommentsPermalink
‘(B) The term ‘qualifying conduit hydropower facility’ means a facility (not including any dam or other impoundment) that is determined or deemed under paragraph (2)(C) to meet the qualifying criteria.CommentsClose CommentsPermalink
‘(C) The term ‘qualifying criteria’ means, with respect to a facility--CommentsClose CommentsPermalink
‘(i) the facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit;CommentsClose CommentsPermalink
‘(ii) the facility has an installed capacity that does not exceed 5 megawatts; andCommentsClose CommentsPermalink
‘(iii) on or before the date of enactment of the Hydropower Regulatory Efficiency Act of 2012, the facility is not licensed under, or exempted from the license requirements contained in, this part.CommentsClose CommentsPermalink
‘(b) Subject to subsection (c), the Commission may grant an exemption in whole or in part from the requirements of this part, including any license requirements contained in this part, to any facility (not including any dam or other impoundment) constructed, operated, or maintained for the generation of electric power which the Commission determines, by rule or order--CommentsClose CommentsPermalink
‘(1) utilizes for such generation only the hydroelectric potential of a conduit; andCommentsClose CommentsPermalink
‘(2) has an installed capacity that does not exceed 40 megawatts.’.CommentsClose CommentsPermalink
(2) in subsection (c), by striking ‘subsection (a)’ and inserting ‘subsection (b)’; andCommentsClose CommentsPermalink
(3) in subsection (d), by striking ‘subsection (a)’ and inserting ‘subsection (b)’.CommentsClose CommentsPermalink
(b) Conforming Amendment- Subsection (d) of section 405 of the Public Utility Regulatory Policies Act of 1978 (

SEC. 5. FERC AUTHORITY TO EXTEND PRELIMINARY PERMIT PERIODS.
Section 5 of the Federal Power Act (

(1) by designating the first, second, and third sentences as subsections (a), (c), and (d), respectively; andCommentsClose CommentsPermalink

(2) by inserting after subsection (a) (as so designated) the following:CommentsClose CommentsPermalink

‘(b) The Commission may extend the period of a preliminary permit once for not more than 2 additional years beyond the 3 years permitted by subsection (a) if the Commission finds that the permittee has carried out activities under such permit in good faith and with reasonable diligence.’.CommentsClose CommentsPermalink
SEC. 6. PROMOTING HYDROPOWER DEVELOPMENT AT NONPOWERED DAMS AND CLOSED LOOP PUMPED STORAGE PROJECTS.
(a) In General- To improve the regulatory process and reduce delays and costs for hydropower development at nonpowered dams and closed loop pumped storage projects, the Federal Energy Regulatory Commission (referred to in this section as the ‘Commission’) shall investigate the feasibility of the issuance of a license for hydropower development at nonpowered dams and closed loop pumped storage projects in a 2-year period (referred to in this section as a ‘2-year process’). Such a 2-year process shall include any prefiling licensing process of the Commission.CommentsClose CommentsPermalink

(b) Workshops and Pilots- The Commission shall--CommentsClose CommentsPermalink

(1) not later than 60 days after the date of enactment of this Act, hold an initial workshop to solicit public comment and recommendations on how to implement a 2-year process;CommentsClose CommentsPermalink

(2) develop criteria for identifying projects featuring hydropower development at nonpowered dams and closed loop pumped storage projects that may be appropriate for licensing within a 2-year process;CommentsClose CommentsPermalink

(3) not later than 180 days after the date of enactment of this Act, develop and implement pilot projects to test a 2-year process, if practicable; andCommentsClose CommentsPermalink

(4) not later than 3 years after the date of implementation of the final pilot project testing a 2-year process, hold a final workshop to solicit public comment on the effectiveness of each tested 2-year process.CommentsClose CommentsPermalink

(c) Memorandum of Understanding- The Commission shall, to the extent practicable, enter into a memorandum of understanding with any applicable Federal or State agency to implement a pilot project described in subsection (b).CommentsClose CommentsPermalink

(d) Reports-CommentsClose CommentsPermalink

(1) PILOT PROJECTS NOT IMPLEMENTED- If the Commission determines that no pilot project described in subsection (b) is practicable because no 2-year process is practicable, not later than 240 days after the date of enactment of this Act, the Commission shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report that--CommentsClose CommentsPermalink

(A) describes the public comments received as part of the initial workshop held under subsection (b)(1); andCommentsClose CommentsPermalink

(B) identifies the process, legal, environmental, economic, and other issues that justify the determination of the Commission that no 2-year process is practicable, with recommendations on how Congress may address or remedy the identified issues.CommentsClose CommentsPermalink

(2) PILOT PROJECTS IMPLEMENTED- If the Commission develops and implements pilot projects involving a 2-year process, not later than 60 days after the date of completion of the final workshop held under subsection (b)(4), the Commission shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report that--CommentsClose CommentsPermalink

(A) describes the outcomes of the pilot projects;CommentsClose CommentsPermalink

(B) describes the public comments from the final workshop on the effectiveness of each tested 2-year process; andCommentsClose CommentsPermalink

(C)(i) outlines how the Commission will adopt policies under existing law (including regulations) that result in a 2-year process for appropriate projects;CommentsClose CommentsPermalink

(ii) outlines how the Commission will issue new regulations to adopt a 2-year process for appropriate projects; orCommentsClose CommentsPermalink

(iii) identifies the process, legal, environmental, economic, and other issues that justify a determination of the Commission that no 2-year process is practicable, with recommendations on how Congress may address or remedy the identified issues.CommentsClose CommentsPermalink

SEC. 7. DOE STUDY OF PUMPED STORAGE AND POTENTIAL HYDROPOWER FROM CONDUITS.
(a) In General- The Secretary of Energy shall conduct a study--CommentsClose CommentsPermalink

(1)(A) of the technical flexibility that existing pumped storage facilities can provide to support intermittent renewable electric energy generation, including the potential for such existing facilities to be upgraded or retrofitted with advanced commercially available technology; andCommentsClose CommentsPermalink

(B) of the technical potential of existing pumped storage facilities and new advanced pumped storage facilities, to provide grid reliability benefits; andCommentsClose CommentsPermalink

(2)(A) to identify the range of opportunities for hydropower that may be obtained from conduits (as defined by the Secretary) in the United States; andCommentsClose CommentsPermalink

(B) through case studies, to assess amounts of potential energy generation from such conduit hydropower projects.CommentsClose CommentsPermalink

(b) Report- Not later than 1 year after the date of enactment of this Act, the Secretary of Energy shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report that describes the results of the study conducted under subsection (a), including any recommendations.CommentsClose CommentsPermalink

Passed the House of Representatives July 9, 2012.CommentsClose CommentsPermalink

Attest:CommentsClose CommentsPermalink

Clerk. 112th CONGRESS 2d Session H. R. 5892 AN ACT